UMATILLA COUNTY BOARD OF COMMISSIONERS

Meeting of April 17, 2008

1:30 p.m., Room 114, County Courthouse, 216 SE 4th St.

Pendleton, Oregon

** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** **

COMMISSIONERS PRESENT:                

Bill Hansell (Chair), Dennis Doherty, Larry Givens

 

PLANNING STAFF PRESENT:                 

J.R. Cook, Heather Haueter

 

COUNTY COUNSEL:                                  

Doug Olsen

 

GUESTS PRESENT:

Michael Robinson, Michael Connors, Travis Hibler, Paul Brunstad

** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** **

NOTE:   THE FOLLOWING IS A SUMMARY OF THE MEETING.  HOWEVER, A TAPE OF THE MEETING IS AVAILABLE AT THE PLANNING DEPARTMENT OFFICE.

 

CALL TO ORDER:

 

Commissioner Hansell called the meeting to order at 1:40 p.m.

 

 

CONTINUED HEARING:

 

APPEAL OF CONDITIONAL USE #C-1103-06.  Flying J, Inc. 1104 Country Hills Drive, Ogden, Utah 84403, applicant and property owner.  Property is 70.39 acres located on southeast quadrant of I-82 and Lamb Road and abuts Westland Road on the east, approx. five miles from the center of the City of Hermiston.  Property consists of two Tax Lots, 200 and 202, on County Assessor’s Map 4N 27 25A.  Applicable zoning on the property is Light Industrial (LI) and Tourist Commercial (TC).

 

CONDITIONAL USE PERMIT allows the following uses on portion of land with TC zoning: restaurant, travel convenience store, automotive fueling stations and accessory improvements (parking, signs, landscaping, etc.).  The following uses would be on portion of land with LI zoning: truck fueling complex, truck service building, truck wash building and accessory improvements. 

 

The proposed uses were approved by the Planning Commission as a conditional use according to Section 152.277(E): other uses similar to the uses permitted or the conditional uses normally located in a Tourist Commercial Zone.  Other applicable criteria includes Sections 152.278, 152.280, 152.304 - 306 and 152.610 - 152.615.

 

 

Staff Report: County Counsel Doug Olson began by explaining that the application was originally received in November 2005.  It went through several hearings with the Planning Commission and was finally approved 8:0.  That decision was appealed to the Board of Commissioners by the appellants, Space Age Fuel and Western Express. 

 

This Board hearing is a de novo review, so new evidence may be received.  A decision may be made today or the Board may decide to continue to a future date.

 

Assistant Planning Director J. R. Cook explained that the reasons for the appeal were summarized in a memo from Planning Director Tamra Mabbott to the Board, dated April 10, 2008.  There were eight grounds for appeal included in an appeal brief from Michael Connors, attorney for the appellants.  The primarily arguments were uses un-allowed in the zone, water rights and transportation issues. 

 

Mr. Cook began with transportation, explaining that a lot of communications had occurred between staff and Perkins Coie, who represents the applicant, and they have submitted a Development Agreement for the roads, and an Irrevocable Consent Agreement (ICA) dealing with specific improvements to Lamb Road and Generation Road.

 

Staff had questions about what standards Generation Road would be improved to because the Development Agreement was vague, stating only that Generation Road would be “improved to County road standards”.  The county has multiple road standards for development, so Mr. Cook hoped the applicant would be able to clarify.

 

Mr. Cook noted that 67 exhibits were included in the Board’s packets and there were two more provided today.  #68 was a letter from Michael Connors dated April 16, 2008; and #69 was a letter from Perkins Coie via email, dated April 17, 2008.

 

Motion:  Commissioner Givens moved to enter Exhibits #1-69 into the record.  Commissioner Doherty seconded.  Motion carried unanimously.

 

Commissioner Doherty asked about the transportation issues, noting a letter from the City of Hermiston requesting that Lamb Road be widened and lighted.  Mr. Cook referred to the Development Agreement, which states what is being proposed based on their transportation analysis, including a 60 foot right-of-way.  Commissioner Hansell noted the last paragraph of the letter from the city where it states their request.  Mr. Olsen added that neither of the city’s requests for widening and lighting had been included in the findings.   

 

There was further discussion about lighting and turn lanes.  Mr. Cook referred to a site plan that was included with the April 9, 2008 letter from Perkins Coie; Exhibit #1 of Exhibit #65 of the Board’s packet. 

 

Commissioner Doherty asked if there was anything showing configuration of the intersection of Lamb and Westland Roads, referring to the county’s Interchange Area Management Plan (IAMP).  He wanted to see if the impact of this project will affect the IAMP.  He noted his concerns about the safety of this intersection for the past 10 years and pointed out the importance of making sure we have proper transportation planning for the entrance and exit from the proposed facility, and the appropriate planning for the intersection where Lamb Road intersects Westland Road.

 

Commissioner Doherty asked about the language of the ICA.  Mr. Olsen explained that it is consistent with what is normally required, with the difference that they cap improvements on the intersection of Lamb and Westland Road, based on their traffic impact study, at 7.6%.  There was some discussion about which engineering company conducted the study specific to this intersection and impacts of the proposed facility.  Mr. Olsen confirmed that Access Engineering conducted the study in September, 2006, which confirms the impact.   

 

Mr. Cook referred to a January 14, 2008 letter from Weden Engineering, which references discussion with the Public Works Director about the comparison between the proposed improvements and the Access Engineering study, but there was no report from Access.    

 

Motion:  Commissioner Givens Larry moved to add the map of the proposed intersection improvements as a result of the Access Engineering study, to the record as Exhibit #70.  Commissioner Doherty seconded.  Motion carried unanimously. 

 

Commissioner Doherty noted that the intersection in Exhibit #70 is the same intersection which is the subject of paragraph three of the ICA, which is exhibit #7.

 

Applicant/Proponent Testimony: Michael Robinson of Perkins Coie, attorney for applicant provided an email exchange of an interaction between his colleague, himself and County Counsel, Doug Olsen to confirm the effective date of Umatilla County Ordinance #2005-09 and the acceptance date of the application.  He requested that it be added to the record.    

 

Motion:  Commissioner Givens moved to add the above mentioned email as Exhibit #71.  Commissioner Doherty seconded.  Motion carried unanimously.

 

Mr. Robinson referred to Commissioner Doherty’s question about the cap named in the ICA.  He explained that the reason for the cap is that there is no cost established at this time or an area wide plan for interchange improvement.  The cap is a reasonable way of estimating responsibility.  If there were no cap there would be no limitation on how much would be reasonable to pay and the applicant does not want to get tagged with an unreasonable expense. 

 

Commissioner Doherty commented that it seemed that the county would be interested in eventually implementing the IAMP, at which time a proportionate share of use of each developer would be determined as represented by proportionate impact.  Mr. Robinson replied that that was what they had done, based on projections.  Their share would likely go down if there were more development at the intersection.  Commissioner Doherty argued that it could also go up if their development had more traffic than expected.  Mr. Robinson replied that the applicant did not want to commit to a plan that has no estimate of cost. 

 

There was some discussion about other ICAs in the subject area.  Mr. Robinson suggested that determination of an acceptable proportionate share be required as a precedent condition of approval, and it could be brought back before the Board for approval.  Commissioner Doherty was agreeable.   

 

Mr. Robinson noted that they had submitted an extension, but not a waiver of the 150 day rule.  They would provide a further extension at the end of the hearing. 

 

Mr. Robinson continued his presentation, noting that since the Planning Commission hearing Generation Road had been vacated and the plat had been recorded, and at the conclusion of this hearing they would extend 150 day waiver for another reasonable period of time.  They had also submitted a letter from Corrine Celko including Oregon Water Resources Department (OWRD) approval of a water rights transfer. 

 

Mr. Robinson explained that this application was before the Board because it has been the Planning Department and Planning Commission’s policy since the Space Age Fuel decision to treat the multiple uses proposed in the application as one conditional use, as opposed to individual uses permitted outright in the LI and TC zones. 

 

One issue that arose in the appellants’ appeal was whether or not the application was filed in a timely manner.  Ordinance #2005-09 was adopted and was effective on November 14, 2005.  The faxed application and fee were physically in the Planning office on November 10, 2005.  Mr. Robinson referred to the first page of the original application, where it was dated and shown paid on that date.  The November 14, 2008 stamp is the date that the mailed copy arrived.   He noted that the Ordinance changes to the TC zone do not apply to this application because it was received in the Planning Department prior to its effective date.

 

Mr. Robinson went on to explain that each proposed use is allowed outright in the zones.  A travel plaza is a similar use found in TC zoning uses.  The similar use provision prevails over the more general use ordinance. Mr. Robinson noted the different titles for other facilities:  Western Express is called a fueling center; Petro is a stopping center, etc.  It is a double standard for Western Express to now argue that the uses are not allowed, since they were approved in the same manner, and there is nothing in relevant case law that says the county can’t accept the application this way. 

 

The traffic development standard is in the Umatilla County Development Code requiring that the applicant demonstrate “no undue burden” and performs a transportation study. The applicant submitted a traffic study by Lancaster Engineering dated December 20, 2007, which concluded that the level of service and the volume capacity ratio are acceptable. 

 

The 2023 analysis is irrelevant, but because of the concerns of the county regarding the Lamb/Westland interchange the applicant has agreed to make it part of the Development Agreement and ICA.  The applicant has coordinated with ODOT and the County Public Works Director and both are comfortable with their traffic study, and the record reflects that their engineer coordinated with both agencies before completing the study. 

 

The Planning Commission found their proposed water access credible.  They will need 35 gallons per minute for the facility and have 50 gallons per minute in water rights.  Needs were based on use of another truck stop of similar size and use.  Mr. Robinson pointed out that if they don’t have sufficient water the development won’t go forward, but there is more than sufficient evidence that they will have adequate water supply.  He also noted that there are no criteria for water.  It is the applicant’s risk. 

 

Mr. Robinson explained that the applicant agreed to meet the City of Hermiston’s request to light Lamb Road and referred to a condition of approval in the Planning Commission’s decision that obligates them to do so.

 

Regarding storm water, Mr. Robinson noted that the site plan includes an area for storm water.  Analysis by a consultant concluded that there is sufficient area.    

 

Mr. Robinson also noted that they have adequate evidence to show that they can treat their waste water.  They looked at three different treatment systems and chose the one that they were confident it was feasible to operate.

 

Mr. Robinson addressed on-site screening, explaining that it only applies in the LI zone for operations within 500 feet of adjoining property, which does not apply in this case.  If it did apply it would require that operations be screened from view.  He cited a case where a petitioner alleged that screening not adequate from every prospective.  Mr. Robinson felt that a reasonable common sense approach interpretation would determine that this would not include things like the view from a bridge or airplane.  He did note that it is feasible for the applicant to screen in a way that complies with the standard.   

 

Mr. Robinson went on to address conditions, requesting that the Board impose a condition for a requirement that where there’s any discretion, a Type II notice must be provided to the public for opportunity to participate in making sure that the conditions are satisfied.  He read language from a LUBA case approving this type of action.   

 

Mr. Robinson read through the precedent and subsequent conditions, explaining which were complete, and which they were still working on.

 

Mr. Robinson noted that the Table of Contents of the Board’s exhibit packets listed Exhibit #7 as received in 2008, but it was actually received in 2006, as can be seen on the document itself. 

 

Mr. Robinson again requested that, if the Board chooses to approve the application, they impose a condition that a Type II notice is given to allow the public input on conditions that are deferred.  

 

Mr. Robinson asked that subsequent condition C be modified to be consistent with the Development Code. 

 

He also asked that the written record be kept open for the applicant only.  The appellant had submitted a large packet of information and the applicant would like to have time to have it reviewed by their consultant.

 

Commissioner Hansell asked that the record reflect that evidence shows that Exhibit #7 was received in 2006, not 2008.

 

Commissioner Doherty asked about the requested change to subsequent condition C.  Mr. Cook replied that it is a blanket subsequent condition.  Mr. Robinson explained that his point was to have the condition relate back to the approval criteria.  They don’t have a problem with screening as it applies to outdoor storage on the site, but they don’t want it extended to the boundary of the entire site. Mr. Cook clarified that there is a difference in criteria between perimeter fencing and screening for storage and the intent of this provision is for storage.

 

Appellant Testimony: Mike Connors, attorney with Davis Wright Tremaine testified on behalf of the appellants.  Mr. Connors acknowledged that there is a history of the county determining that the proposed use is appropriate, and he respected that, so he wouldn’t address that issue, although he believed it to still be an issue.  However, there were several issues that he felt would affect the county and needed to be addressed.

 

First was traffic, particularly the problematic intersection of Lamb, Westland and Walker roads.  Mr. Connors noted that the applicant acknowledges that they will impact the intersection, but the question is what is the impact?  The problem with the applicant’s traffic analysis is that it significantly underestimates the amount of traffic that would be generated.  He based this on information that the appellant’s engineers generated, as well as data from comparable truck stops and analysis that Kittelson and Associates provided for the county’s IAMP.

 

The problem with how the applicant estimated traffic is that they used the ITE Manual, which is commonly used by traffic engineers, and categorized the facility as an automobile gas station.  This is flawed because there are other uses associated with the facility that are not included in their analysis. 

 

The second problem is that an auto gas station is different than a truck stop.  The county’s Kittelson study recognized that there was no category of truck stop, so they used the Pilot facility in Hermiston.  The appellant’s engineer did this at Flying J’s Troutdale facility and traffic counts demonstrated that there would be a greater number of trips than the Flying J application indicates.  The percentage of their share of contribution for improvements is based on the estimate of traffic generation and it is flawed because it does not account for all the uses. 

 

The second issue is that the concept of the ICA does not obligate them to make any improvements or contributions.  It just says that when the county determines a plan and comes up with funding, they won’t object.  It is already determined to be an unsafe intersection and it is fairly certain that their facility would be open before solutions for the intersection are complete. 

 

Mr. Connors not only thought that deferring the traffic issue not legal, but he also felt that the county just shouldn’t.  He referred to Development Code Section 152.017, which states what the obligations of the applicant are, and that the facility should not significantly impact or cause undue burden.  There is nothing in the Code that says these issues can be deferred.  The must be mitigated now.  The applicant has means to address the problem by getting other truck stops to cooperate, or come up with some sort of reimbursement mechanism.  Mr. Connors urged the Board to use this as opportunity to force the applicant to figure out how to fix the problem.

 

Mr. Connors also pointed out that there area a number of outs and protections for Flying J written into the ICA.  The first is the 7.6% cap.  There is a ceiling but no floor.  Also, there in no way of knowing how many other users will be participating.  There is no legal obligation for a cap.  Second is that what they’re agreeing to is not to object.  Language in the ICA reserves every possible objection that they may have and defeats the purpose of having an ICA.  Plus, they’re basing their percentage on future uncertainties.

 

The Development Agreement primarily addresses Lamb Road improvements.  They agree to improvements on a portion of Lamb Road, but absolve themselves from responsibility if it is not done correctly. 

 

Mr. Connors talked about deferring criteria through conditions.  He noted that in the Petro case, LUBA determined that criteria cannot be deferred because there is no opportunity for public input.  The county also loses leverage.  He felt the applicant should be required to redo the traffic study, figure out what the improvement will be and how it will get fixed.  From the county perspective, it is important to weigh these issues and make sure that they are getting solid analysis. 

 

The third issue was water.  The applicant says that water is their problem, but the county typically requires that adequate water be demonstrated and does have a specific code provision.  If the applicant’s needs exceed availability then there is potential for impact on other users.  If this happens it is then left up to enforcement, which is inadequate. 

 

At the Planning Commission level the appellant’s water consultant, GSI produced a letter dated January 23, 2008.  (There was discussion about whether this letter had made it into the record because it was not reflected on the original table of contents for the Board packets.  It was determined that it had been included and was Exhibit #57.)  What this letter showed was that there was nothing to support the letter from the applicant’s consultant to prove what their water needs will be.  Their own figures don’t meet what they say their peak demand is. 

 

The appellant’s consultant picked two existing Flying J facilities and acquired use numbers.  This showed that the overall annual demand is almost twice what the applicant is showing for the proposed facility. 

 

The fourth issue was wastewater/storm water.  Nothing regarding waste and storm water was brought before the commission and no plans had been provided to the county.  There was no explanation why they haven’t provided this information already. 

 

The fifth issue was deferring compliance through conditions of approval.  These are basic and fundamental components of projects that should be answered.  Even if they are deferred, the applicant is asking defer to a Type II review process, but it needs to be equivalent to the original process, which is Type III.  The Type II process is administrative and uses the appeal process to raise issues.  Mr. Connors argued that the applicant doesn’t even have a basic plan for some of the conditions they are wanting deferred. 

 

Mr. Connors addressed Mr. Robinson’s request for the right to closing argument.  The basis is statutory, which allows for the Board to leave the record open and give the applicant final argument, but this only applies in the initial hearing process, which was actually the Planning Commission hearing.  The appellant objects to just the applicant having closing argument.  Mr. Connors requested that both sides be allowed argument only and no new evidence. 

 

Commissioner Givens noted the statement that there is no mechanism to manage water usage, but he pointed out that there is a process, although complaint driven.  Mr. Connors argued that it puts other water right holders in a position of defending their rights.  Enforcement is not as good as ensuring now. 

 

Commissioner Givens pointed out that typically, if transfer rights state a certain amount, it is monitored by a meter.  If they go over that the applicant would be putting a vast amount of resources at stake, knowing that if they go over their right they have a lot to lose.  Mr. Connors agreed that this might create some incentive, but the Code requires the county to preserve and protect water resources and this is in a critical groundwater area. 

 

Mr. Cook added that many conditions of approval rely on water to complete, but how do we prove that they can meet the conditions of approval if we don’t know that the water supply is there to do so.  That particular condition is very vague and confusing in a critical groundwater area.  They are required to meter and report, but at that point the development is there and if they go over who is at fault?  Commissioner Givens again noted that the client is the one at risk of losing their investment if they overuse their right.    

 

Commissioner Doherty referred to the appellant comment that the applicant does not have adequate water to meet their peak demand.  Mr. Connors replied that what the applicant’s own water consultant cites as their instantaneous peak demand is greater than their water right. 

 

Commissioner Doherty asked if Mr. Cook agreed that supply was not adequate.  Mr. Cook replied that they have obtained a water source.  Whether or not it was adequate he could not determine.

 

Commissioner Doherty also asked about a letter from the fire district about fire provisions.  Mr. Cook replied that staff had asked the fire districts for a copy of their fire provisions because the county does not have a copy of each district’s code.  Mr. Robinson noted that Exhibit J of his January 14, 2008 letter, which is Exhibit # 52, was a letter from Tom Bohm, Fire Marshall requiring a 20,000 gallon fire reserve.  He also referred to the minutes of the Planning Commission hearing which state that they will actually have two 40,000 gallon tanks. 

 

Commissioner Doherty noted that one of the conditions was to provide proof of compliance with fire and emergency services requirements.  Mr. Robinson replied that it is really just administerial, done through the course of acquiring a zoning permit. 

 

Commissioner Doherty asked for staff clarification.  Mr. Cook explained that staff usually calls the fire district to clarify whether a proposed plan will work and make a finding to that affect.  The Planning Commission found that there was sufficient supply and the site plan was adequate. 

 

Commissioner Doherty was concerned about the need to make some kind of finding on water.  Mr. Cook replied that if the Board found that the applicant had sufficient water right they could remove precedent condition #6 requiring documentation that an adequate water source had been obtained.  The Board could find that a water supply source had been quantified.  Mr. Connors interjected that adequate, at a minimum, is to show that their water right exceeds accurate water need, yet evidence in the record indicates that water use could be double their water right.  Mr. Olsen added that another problem is that the county doesn’t have a Code provision requiring proof. 

 

Commissioner Givens commented that OWRD only allows the gallonage of your permit, but you can use more per hour at peak times as long as you don’t go over your yearly limit.  If you go over that then you’re cut off.  Mr. Connors asked if the county wants to be put in the position of dealing with that, and he disagreed that there is no criteria that requires water analysis.  He noted the provision to preserve and protect in the critical groundwater area, and it has been the county’s historical policy.  Burden should be on the applicant to resolve the problem.

 

Mr. Robinson commented that it is not as complicated as it appears.  There are three issues.  First, the fire district requires an onsite water source for fire control of 20,000 gallon water reserve and the district will supplement another 10,000.  From the minutes, Mr. Weden notes portable water in two 40,000 gallon containers.  This plus the fire district supplement water is 90,000 gallons.

 

Second, is the question of the water requirement for this use.  The requirement is 30,000 gallons and the applicant has a water right for 50,000.  Plus, they have an 80,000 gallon water reserve that could be used if a spike in use were to occur.  Third, there are no approval criteria for preservation of water.  The conditional use section says that the decision maker can impose a condition regarding protection of water resources, but this facility cannot have a negative impact when it’s using an existing water right.  Mr. Robinson pointed out that the appellant, Western Express had themselves purchased an existing water right for their own facility.   He felt there was ample evidence in the record to show that they meet any water requirements and would not be adversely affecting water.

 

Mr. Connors argued that the only evidence from the applicant is a one page letter from their water consultant with nothing to back it up his figures.  Mr. Porfily testified at Planning Commission that he did not determine water need, but was told what the need was and based on that, acquired rights that would satisfy that.  The appellants’ position is that the need is underestimated by half.  The applicant is also stating that they will have storage capacity for fire purposes, but that’s presuming that they will have excess.  They won’t if their water usage exceeds their right.  The county has historically required evidence of water need, and based on numbers from the applicant’s other facilities, they do not have enough water right. 

 

Commissioner Doherty addressed Mr. Connors about traffic concerns, noting that Mr. Connors had previously stated that the Board had the right to require the applicant to mitigate the intersection.  Commissioner Doherty wondered about proportionality.  Mr. Connors replied that there were two issues; getting it done and cost.   He pointed out that the Code talks about what mitigation measures are available to an applicant and referred to page 10 of the Planning Commission findings where it quotes that section of the code.  That provision requires improvements, not an agreement to pay a proportionate share in the future. 

 

Commissioner Doherty commented that Mr. Connors was basically saying that the Board had the authority to impose the whole cost of improvement on the applicant, but Commissioner Doherty questioned the Boards ability to assure the applicant that they would be reimbursed by other parties.  Mr. Connors replied that it could be addressed through a development agreement or local improvement district, providing that the county will assure that future projects have a “late comers” reimbursement mechanism.  The Code requires that the applicant should be required to fix the problem and there are mechanisms to ensure that they are reimbursed. 

 

Commissioner Doherty noted that Mr. Connors suggested that the applicant be required to redo their traffic study, but he pointed out that when people do their own traffic studies there is always suspicion that maybe they’re not really credible.  How would a new study resolve anything?  Mr. Connors replied that they just request that the applicant use a method consistent with what traffic engineers are supposed to use; using comparable studies of existing truck stops for a basis, since the ITE manual doesn’t have a category for truck stops.   

 

Agency Testimony: None

 

Rebuttal Testimony:  Mr. Robinson addressed the procedural issues first.  First, he disagreed about the statute on final written argument.  In a setting like this, the Board doesn’t have to keep the record open.  The applicant always has the burden of proof and last word.  He requested that only final written argument be allowed and no new testimony.  He also asked that if the Board chooses not to grant his request that they allow the written record to remain open seven days for both parties. 

 

There was further discussion about final written argument.  Mr. Connors objected to consultant work being included in the closing argument, because that would be considered expert evidence.  He requested only legal argument be allowed; no new evidence.  Mr. Robinson argued that a letter from a consultant that relies on evidence already in the record would not be new evidence. 

 

Commissioner Doherty asked how it would affect the issued if the Board were to decide to require a new traffic study.  Mr. Robinson first requested that, if the Board requires a new study that they be precise in what’s missing because there are already two studies in the record.  Then he recommended keeping the written record open for more than 7 days because it would take some time to submit a new study. 

 

Mr. Robinson went on to address the substantive issues, starting with traffic.  The December 20, 2007 traffic letter predicted that all intersections would operate effectively.  The AM peak hour level of service leaves more that 2/3 of capacity remaining.  Neither ODOT, nor the County Public Works Director has found the applicant’s proposal flawed or requested a new analysis.  Their engineer used the same analysis as the nearby Barton application, removing only the hotel, and the Board approved that same analysis.    

 

Mr. Robinson noted that the appellants’ engineer, DKS used a truck stop in an urban area for their analysis, where there are much different traffic patterns.  He also noted that Mr. Connors stated they were low balling their trip generation, but they used an ITE model, the Barton traffic study, and neither ODOT nor the Public Works Director disagreed with their figures.  The only one who disagreed was the opponent’s engineer.

 

Regarding the safety of the intersection, Mr. Robinson pointed out that there had only been eight accidents over the course of five years.  Even if deemed unsafe, requiring the applicant to improve the intersection would not ensure increased safety.  Mr. Robinson also noted that no other applicant had been required to make all improvements to the intersection.  There is no legal mechanism to require existing developers to pay back Flying J for improvements.  They would have to wait for new developers.  

 

Mr. Robinson felt the most equitable way to impose improvements would be through an ICA.  If the Board and staff feel it needs improvement, he would be happy to make changes. 

 

Mr. Robinson referred to Mr. Connor’s comments about the ICA, noting that it is common for the consenter to say that they agree to improvements, but they should never waive their right to remonstrate.  He also explained that the 7.6% cap was based on ITE numbers and Flying J’s share as calculated in the IAMP. 

 

The warranty on improvements to Lamb Road means that the applicant will construct the road to County standards, but is not going to warrant the road after construction.  They would agree to a one year maintenance bond, but they are not willing to give a perpetual warranty. 

 

Mr. Robinson noted that Mr. Connors had compared this application to the Petro case, but it really is not the same.  The Petro decision was remanded by LUBA because the county improperly relied on deviation to access spacing standards.  In Petro LUBA also noted lack of evidence on the impact.  In this case there are actually two traffic studies, both showing that there would be no adverse impact on the intersection or any of the ramps to I-84. 

 

Mr. Robinson addressed water, stating that there is nothing to say that the county can impose a condition, and there would be no water resource impact.  The Planning Commission wanted the applicant to provide documentation that an adequate water source had been obtained, and they have two pieces; a letter from their consultant stating need and a letter from Mr. Porfily stating that water rights had been secured.  The appellant’s evidence looked at two sites only, and doesn’t account for storage or water conservation methods.  Mr. Robinson also noted that the applicant’s site plan shows an area for storage and treatment of wastewater and storm water. 

 

Mr. Robinson did not feel the applicant was deferring compliance through conditions as Mr. Connors suggested.  Some conditions simply can’t be completed until after the zoning permit is acquired. 

 

In response to Mr. Connors’ argument that they must use a Type III review, Mr. Robinson stated that he was also not aware of any law requiring equivalent procedures for review of conditions of approval for new public comment on plans.  Type II allows notice and opportunity for public comment, which is all that’s required.

 

The condition of approval imposed by Planning Commission requiring widening of Lamb Road and street lighting on Lamb and Westland Roads addresses the City of Hermiston’s request.  The city wanted the Lamb Road widened to facilitate trucks turning in and out, but they don’t to need widen the full length of Lamb Road to achieve this.  Condition #9 achieves what the city is asking for. 

 

Mr. Robinson did not think the applicant could be required to repair the entire intersection, but if the Board feels they need to revise how they determined proportionality then they would be willing to do that.    

 

To conclude, Mr. Robinson requested that the Board grant final written argument to the applicant only.  If not, he requested that they leave the evidentiary record open for both parties for 14 days for final written argument, with 7 days for written rebuttal for the applicant. 

 

Mr. Robinson also noted that if the Board requires the applicant to submit a new traffic study and revised ICA, he would request specific direction as to how the Board wants them to be done. 

 

Hearing Closed; Deliberation and Decision:  Commissioner Doherty commented that he would like to extend closing argument to the applicant only, but the line between what is evidence and what is not is fine, and he did not want to get caught up in what can and can’t be attached.  He would put the burden on Mr. Connors to test that rule. 

 

Commissioner Doherty explained that his interest in redoing the traffic study was tied to the ICA.  With a cap involved it seems that the study would be helpful and informative to evaluate if proposed improvements are sufficient and whether a 7.6% cap is adequate.  

 

Commissioner Hansell agreed with Commissioner Doherty on granting Mr. Robinson’s request for final written argument.  If Mr. Connors wants to challenge at LUBA he is able to do that. 

 

He was comfortable with the traffic study, especially since the Public Works Director and ODOT had signed off on the current study. 

 

Mr. Robinson stated that if the applicant is allowed final written argument they can address the wording of the ICA at that time.  He would be happy to come back with a Type II review and test the new language if necessary. 

 

Commissioner Givens would also agree to grant written testimony to the applicant only.

He was not interested in requiring a new study, but he was also not comfortable with the 7.6% cap.

 

There was discussion about scheduling and when written argument would be due.  It was decided that Mr. Robinson’s written argument would be due April 24, 2008 at 5:00 p.m., and deliberation would be May 8, 2008 at 9:00 a.m. during the Administrative meeting in Room 121 of the County Courthouse.  Mr. Robinson would extend the 150 day waiver to May 9, 2008. 

 

Commissioner Hansell closed the hearing for testimony and the request by the applicant for final written argument was granted, being due April 24, 2008, by the close of business.  The meeting would reconvene May 8, 2008 at 9:00 a.m. in Room 121 of the County Courthouse.    

 

 

APPROVAL OF MINUTES:

 

The minutes of November 27, 2007; January 8, 2008; and January 31, 2008 were approved as submitted. 

 

 

ADJOURNMENT:

 

The meeting was adjourned at 5:30 p.m.

 

 

Respectfully submitted,

 

 

 

Heather Haueter

Secretary